Co-Mac Warehouse Build - Week 21

Continued progress as we conclude week 21 of the Co-Mac Warehouse Build. Learn about what happened this week...


Progress Summary

Monday (7/3/22)

- Lifted beam up on grid C.1

- Ready to lift grid 8/9 north end.


Tuesday (8/3/22)

- Lifted grid 8/9 up into place north end.


Wednesday (9/3/22)

- Bracing up building to get it straight.


Thursday (10/3/22)

- Roofers on site put grid 11 - 12 centre mesh on roof.

- Bracing building.


Friday (11/3/22)

- ABC working on office floor.


Contractors:

Arthur Brown Construction - www.arthurbrown.co.nz

BTW Company - www.btw.nz

Custom Construction - www.customconstruction.co.nz

Drillco - www.drillco.co.nz

Taranaki Civil Construction - https://www.tccl.co.nz/