Co-Mac Warehouse Build - Week 12
Continued progress as we conclude week 12 of the Co-Mac Warehouse Build. Learn about what happened this week...

Progress Summary
Wednesday (5/1/22)
- Stripping boxing off central pads and north side.
Thursday (6/1/22)
- Central post pour.
- Almost ready for pouring in the office.
Friday (7/1/22)
- North boxing ourdie removed.
- Central posts ready to pour.
Contractors:
Arthur Brown Construction - www.arthurbrown.co.nz
BTW Company - www.btw.nz
Custom Construction - www.customconstruction.co.nz
Drillco - www.drillco.co.nz
Taranaki Civil Construction - https://www.tccl.co.nz/