Co-Mac Warehouse Build - Week 1

What a exciting week! Our Co-Mac Warehouse Build has officially started with contractors arriving on site to begin the build. The plan is on track and progress is underway.


Progress Summary


The security fence has gone up and it is really starting to look like a building site. BTW is on site and laying out the grid. Along with Arthur Brown Construction who has started putting in the profiles.


We've had the Drillco under borer arrive for drilling the air conditioning ground water pipes.


Contractors:

Arthur Brown Construction - www.arthurbrown.co.nz

BTW Company - www.btw.nz

Drillco - www.drillco.co.nz



Weather Review


It was a bit windy this week but we were fortunate to only have a few rain showers on Tuesday and Wednesday, with the other days great working weather.




Weekly Project Rating


Weekly Grade: 9/10

All in all it was a good week and nice to see the project underway with progress been made.






Great buildings come from great people, and all challenges are solved by the execution of a great plan.