Progress Summary

Monday (6/12/21)

- Slow rain.

- South side braces off shutters.

- West side braces off outside.

- Some West side braces off inside.


Tuesday (7/12/21)

- Slight drizzle of rain.

- Central pads poured for posts in warehouse.

- South boxing stripped.


Wednesday (8/12/21)

- West side outside bracing stripped.

- East and North boxing in place.

- Internal pad boxing stripped.


Thursday (9/12/21)

- East outside boxing levelled.


Friday (10/12/21)

- North outside boxing levelled.


Contractors:

Arthur Brown Construction - www.arthurbrown.co.nz

BTW Company - www.btw.nz

Custom Construction - www.customconstruction.co.nz

Drillco - www.drillco.co.nz

Taranaki Civil Construction - https://www.tccl.co.nz/



Weather Review