Co-Mac Warehouse Build - Week 8
Continued progress as we conclude week 8 of the Co-Mac Warehouse Build. Learn about what happened this week...

Progress Summary
Monday (29/11/21)
- Reinforcing finished.
- Started on doorway floor connections.
- 3/4 along South side putting in the hold down bolts.
Tuesday (30/11/21)
- Raining
- South side ready to be pour.
- West side ready to pour.
- North side almost ready.
Wednesday (1/12/21)
- Ready to our ring foundation.
- Steel ready to be made up for the main internal pads for the internal posts.
Thursday (2/12/21)
- Over half of the foundation ring done.
- 4:30am concrete pour started.
- South and West side finished.
- Four internal footings with reinforcing installed are ready to pour.
Friday (3/12/21)
- Some boxing brazes stripped off on the West side.
- Centre reinforcing done for the main pads.
Contractors:
Arthur Brown Construction - www.arthurbrown.co.nz
BTW Company - www.btw.nz
Custom Construction - www.customconstruction.co.nz
Drillco - www.drillco.co.nz
Taranaki Civil Construction - https://www.tccl.co.nz/
Weather Review


“Great buildings come from great people, and all challenges are solved by the execution of a good plan.”