Co-Mac Warehouse Build - Week 49
Continued progress as we conclude week 49 of the Co-Mac Warehouse Build. Learn about what happened this week...

Progress Summary
Monday (19/9/22)
- Working on shelving.
- Working on air conditioing.
- Electrians working.
- Working on canopy.
- Working on roof.
- Working on office.
- Working on fire alarms.
- Working on driveway.
Tuesday (20/9/22)
- Working on shelving.
- Working on air conditioing.
- Electrians working.
- Working on canopy.
- Working on sliding doors.
- Working on office.
- Working on fire alarms.
- Working on driveway.
Wednesday (21/9/22)
- Working on shelving.
- Working on air conditioing.
- Electrians working.
- Working on canopy.
- Working on sliding doors.
- Working on office.
- Working on fire alarms.
- Working on driveway.
Thursday (22/8/22)
- Working on shelving.
- Working on air conditioing.
- Electrians working.
- Working on canopy.
- Working on sliding doors.
- Working on office.
- Working on fire alarms.
- Working on driveway.
Friday (23/9/22)
- Working on shelving.
- Working on air conditioing.
- Electrians working.
- Working on sliding doors.
- Working on office.
- Working on fire alarms.
- Working on driveway.
Contractors:
Arthur Brown Construction - www.arthurbrown.co.nz
BTW Company - www.btw.nz
Custom Construction - www.customconstruction.co.nz
Drillco - www.drillco.co.nz
Taranaki Civil Construction - https://www.tccl.co.nz/
Weather Review


“Great buildings come from great people, and all challenges are solved by the execution of a good plan.”