Co-Mac Warehouse Build - Week 49

Continued progress as we conclude week 49 of the Co-Mac Warehouse Build. Learn about what happened this week...


Progress Summary

Monday (19/9/22)

- Working on shelving.

- Working on air conditioing.

- Electrians working.

- Working on canopy.

- Working on roof.

- Working on office.

- Working on fire alarms.

- Working on driveway.




Tuesday (20/9/22)

- Working on shelving.

- Working on air conditioing.

- Electrians working.

- Working on canopy.

- Working on sliding doors.

- Working on office.

- Working on fire alarms.

- Working on driveway.


Wednesday (21/9/22)

- Working on shelving.

- Working on air conditioing.

- Electrians working.

- Working on canopy.

- Working on sliding doors.

- Working on office.

- Working on fire alarms.

- Working on driveway.


Thursday (22/8/22)

- Working on shelving.

- Working on air conditioing.

- Electrians working.

- Working on canopy.

- Working on sliding doors.

- Working on office.

- Working on fire alarms.

- Working on driveway.


Friday (23/9/22)

- Working on shelving.

- Working on air conditioing.

- Electrians working.

- Working on sliding doors.

- Working on office.

- Working on fire alarms.

- Working on driveway.



Contractors:

Arthur Brown Construction - www.arthurbrown.co.nz

BTW Company - www.btw.nz

Custom Construction - www.customconstruction.co.nz

Drillco - www.drillco.co.nz

Taranaki Civil Construction - https://www.tccl.co.nz/



Weather Review






































Great buildings come from great people, and all challenges are solved by the execution of a good plan.