Continued progress as we conclude week 47 of the Co-Mac Warehouse Build. Learn about what happened this week...


Progress Summary

Monday (5/9/22)

- Working on office.

- Electrians working.

- Working on roof.

- Working on canopy.

- Working on air conditioning.


Tuesday 6/9/22)

- Working on office.

- Electrians working.

- Working on roof.

- Working on canopy.

- Working on air conditioning.

- Working on sliding doors.


Wednesday (7/9/22)

- Working on office.

- Electrians working.

- Working on roof.


Thursday (8/9/22)

- Working on office.

- Electrians working.

- Working on roof.

- Working on air conditioning.


Friday (9/9/22)

- Working on office.

- Electrians working.

- Working on roof.

- Working on air conditioning.


Saturday 10/9/22

- Electrical work.



Contractors:

Arthur Brown Construction - www.arthurbrown.co.nz

BTW Company - www.btw.nz

Custom Construction - www.customconstruction.co.nz

Drillco - www.drillco.co.nz

Taranaki Civil Construction - https://www.tccl.co.nz/



Weather Review