Co-Mac Warehouse Build - Week 45
Updated: Oct 19, 2022
Continued progress as we conclude week 45 of the Co-Mac Warehouse Build. Learn about what happened this week...

Progress Summary
Monday (22/8/22)
- Floor tidying.
- Electrians working.
- Linings going on.
- Working on roof.
Tuesday (23/8/22)
- Floor tidying.
- Electrians working.
- Linings going on.
- Working on roof.
Wednesday (24/8/22)
- Door made.
- Working on Canopy.
- Linings going on.
- Working on roof.
- Electrians working.
- Working on floor.
Thursday (25/8/22)
- Working on canopy.
- Roller doors in.
- Electrians working.
- Lining going on.
- Working on roof.
- Working on floor.
Friday (26/8/22)
- Working on canopy.
- Electrians working.
- Working on roof.
- Working on floor.
Contractors:
Arthur Brown Construction - www.arthurbrown.co.nz
BTW Company - www.btw.nz
Custom Construction - www.customconstruction.co.nz
Drillco - www.drillco.co.nz
Taranaki Civil Construction - https://www.tccl.co.nz/
Weather Review


“Great buildings come from great people, and all challenges are solved by the execution of a good plan.”