Co-Mac Warehouse Build - Week 44
Updated: Oct 19, 2022
Continued progress as we conclude week 44 of the Co-Mac Warehouse Build. Learn about what happened this week...

Progress Summary
Monday (15/8/22)
- Electricians working.
- Plumblers working.
- Working on roof and cladding.
Tuesday (16/8/22)
- Electricians working.
- Plumblers working.
- Working on roof and cladding.
Wednesday (17/8/22)
- 1/2 floor poured.
- Electricians working.
- Plumblers working.
- Inside wall linings going on.
Thursday (18/8/22)
- Air conditioning being done.
- Floor finished.
- Electricians working.
- Wall linings going on.
Friday (19/8/22)
- Floor tidied up.
- Electricians working.
- Wall linings going on.
Contractors:
Arthur Brown Construction - www.arthurbrown.co.nz
BTW Company - www.btw.nz
Custom Construction - www.customconstruction.co.nz
Drillco - www.drillco.co.nz
Taranaki Civil Construction - https://www.tccl.co.nz/
Weather Review


“Great buildings come from great people, and all challenges are solved by the execution of a good plan.”