Co-Mac Warehouse Build - Week 43
Updated: Oct 19, 2022
Continued progress as we conclude week 43 of the Co-Mac Warehouse Build. Learn about what happened this week...

Progress Summary
Monday (8/8/22)
- Working on concrete floor.
- Working on office floor and walls.
Tuesday (9/8/22)
- Working on concrete floor.
- Working on office floor and walls.
Wednesday (10/8/22)
- Working on concrete floor.
- Working on office floor and walls.
Thursday (11/8/22)
- Working on concrete floor.
- Working on office floor and walls
- Working on cladding.
- Working on roof.
Friday (12/8/22)
- Working on concrete floor.
- Working on office floor and walls
- Working on cladding.
- Working on roof.
Contractors:
Arthur Brown Construction - www.arthurbrown.co.nz
BTW Company - www.btw.nz
Custom Construction - www.customconstruction.co.nz
Drillco - www.drillco.co.nz
Taranaki Civil Construction - https://www.tccl.co.nz/
Weather Review


“Great buildings come from great people, and all challenges are solved by the execution of a good plan.”