Co-Mac Warehouse Build - Week 41

Continued progress as we conclude week 41 of the Co-Mac Warehouse Build. Learn about what happened this week...


Progress Summary

Monday (25/7/22)

- Working on office floor and walls.



Tuesday (26/7/22)

- Working on south side wall.

- Working on floor prep.

- Working on office floor and walls.


Wednesday (27/7/22)

- Working on south side wall.

- Working on floor prep.

- Working on office floor and internal walls.


Thursday (28/7/22)

- Working on south side wall.

- Working on floor prep.

- Working on office floor and internal walls.


Friday (29/7/22)

- Working on floor prep.

- Working on office floor and walls.

- Concrete under Canopy cut.



Contractors:

Arthur Brown Construction - www.arthurbrown.co.nz

BTW Company - www.btw.nz

Custom Construction - www.customconstruction.co.nz

Drillco - www.drillco.co.nz

Taranaki Civil Construction - https://www.tccl.co.nz/



Weather Review

































Great buildings come from great people, and all challenges are solved by the execution of a good plan.