Progress Summary

Monday (18/7/22)

- Floor prep with laser bobcat.

- Working on floor prep.

- Working on office floor and frames.



Tuesday (19/7/22)

- Floor prep with laser bobcat

- Working on floor prep.

- Working on office floor and frames.

- Working on roof.


Wednesday (20/7/22)

- Floor prep.

- Office floor and frames.


Thursday (21/7/22)

- Setting up for canopy floor pour.

- Working on office floor.


Friday (22/7/22)

- Floor of canopy poured.

- Working on end wall.

- Working on roof.

- Floor prep done for concrete slab.



Contractors:

Arthur Brown Construction - www.arthurbrown.co.nz

BTW Company - www.btw.nz

Custom Construction - www.customconstruction.co.nz

Drillco - www.drillco.co.nz

Taranaki Civil Construction - https://www.tccl.co.nz/



Weather Review