Co-Mac Warehouse Build - Week 38

Continued progress as we conclude week 38 of the Co-Mac Warehouse Build. Learn about what happened this week...


Progress Summary

Monday (4/7/22)

- End wall cladding going on.

- Roofing going on.

- Working on offices.

- Electrical lighting being installed.



Tuesday (5/7/22)

- End wall cladding going on.

- Roofing going on.

- Working on offices.

- Electrical lighting being installed.


Wednesday (6/7/22)

- Roofing going on.

- Working on offices.

- Electrical lighting being installed.


Thursday (7/7/22)

- Fire gib on ceiling going up.

- Office floor going down.

- Electrical lighting being installed.


Friday (8/7/22)

- Fire jib on ceiling going up.

- Electrical lighting being installed.

- Office floor going down.




Contractors:

Arthur Brown Construction - www.arthurbrown.co.nz

BTW Company - www.btw.nz

Custom Construction - www.customconstruction.co.nz

Drillco - www.drillco.co.nz

Taranaki Civil Construction - https://www.tccl.co.nz/



Weather Review


























Great buildings come from great people, and all challenges are solved by the execution of a good plan.