Monday (4/7/22)
- End wall cladding going on.
- Roofing going on.
- Working on offices.
- Electrical lighting being installed.
Tuesday (5/7/22)
- End wall cladding going on.
- Roofing going on.
- Working on offices.
- Electrical lighting being installed.
Wednesday (6/7/22)
- Roofing going on.
- Working on offices.
- Electrical lighting being installed.
Thursday (7/7/22)
- Fire gib on ceiling going up.
- Office floor going down.
- Electrical lighting being installed.
Friday (8/7/22)
- Fire jib on ceiling going up.
- Electrical lighting being installed.
- Office floor going down.
Contractors:
Arthur Brown Construction - www.arthurbrown.co.nz
BTW Company - www.btw.nz
Custom Construction - www.customconstruction.co.nz
Drillco - www.drillco.co.nz
Taranaki Civil Construction - https://www.tccl.co.nz/