Continued progress as we conclude week 37 of the Co-Mac Warehouse Build. Learn about what happened this week...


Progress Summary

Monday (27/6/22)

- Work on office floor.

- Electrical light wiring going in.



Tuesday (28/6/22)

- Working on office floor.

- Electrical light wiring going in.

- Roof on up to grid line 9.


Wednesday (29/6/22)

- Frames up internally started.

- Working on office floor.

- Electrical light wiring going in main building.


Thursday (30/6/22)

- Canopy south ready to pour.

- Working on lighting in warehouse.

- Working on office floors and internal frames.


Friday (1/7/22)

- Working on lighting in warehouse.

- Working on office floors and internal frames.

- Working on roof flashings.



Contractors:

Arthur Brown Construction - www.arthurbrown.co.nz

BTW Company - www.btw.nz

Custom Construction - www.customconstruction.co.nz

Drillco - www.drillco.co.nz

Taranaki Civil Construction - https://www.tccl.co.nz/



Weather Review


























Great buildings come from great people, and all challenges are solved by the execution of a good plan.

0 views0 comments

Recent Posts

See All
bottom of page