Co-Mac Warehouse Build - Week 36

Continued progress as we conclude week 36 of the Co-Mac Warehouse Build. Learn about what happened this week...


Progress Summary

Monday (20/6/22)

- Internal frames going in.

- Flashing worked on.

- Final part going in for steel structure.



Tuesday (21/6/22)

- Wiring for lights going in.

- Internal frames going up.

- Flashing being done on roof.

- Wall sheets going up.

- Clearing out main building of material for wiring for electric lights going in.


Wednesday (22/6/22)

Progress on:

- Internal frames.

- Roofing.

- Structure.


Thursday (23/6/22)

Progress on:

- Wall Cladding.

- Roof 1/2 complete.

- Floor.

- Structure.


Friday (24/6/22)

Holiday



Contractors:

Arthur Brown Construction - www.arthurbrown.co.nz

BTW Company - www.btw.nz

Custom Construction - www.customconstruction.co.nz

Drillco - www.drillco.co.nz

Taranaki Civil Construction - https://www.tccl.co.nz/



Weather Review






















Great buildings come from great people, and all challenges are solved by the execution of a good plan.