Co-Mac Warehouse Build - Week 35
Continued progress as we conclude week 35 of the Co-Mac Warehouse Build. Learn about what happened this week...

Progress Summary
Monday (13/6/22)
- Working on raised floor.
- Working on canopy floor boxing.
Tuesday (14/6/22)
- Working on raised floor.
- Working on canopy floor boxing.
Wednesday (15/6/22)
- Canopy boxing almost done.
- Working on raised floor.
- Frames arrived for walls - internal.
Thursday (16/6/22)
- Canopy boxing done ready for mesh.
- Working on raised floor.
- Working on structure.
Friday (17/6/22)
- Roof done on south side lower side except clear lights.
- Structure almost done with girts and studs outside.
Contractors:
Arthur Brown Construction - www.arthurbrown.co.nz
BTW Company - www.btw.nz
Custom Construction - www.customconstruction.co.nz
Drillco - www.drillco.co.nz
Taranaki Civil Construction - https://www.tccl.co.nz/