Co-Mac Warehouse Build - Week 35

Continued progress as we conclude week 35 of the Co-Mac Warehouse Build. Learn about what happened this week...


Progress Summary

Monday (13/6/22)

- Working on raised floor.

- Working on canopy floor boxing.


Tuesday (14/6/22)

- Working on raised floor.

- Working on canopy floor boxing.


Wednesday (15/6/22)

- Canopy boxing almost done.

- Working on raised floor.

- Frames arrived for walls - internal.


Thursday (16/6/22)

- Canopy boxing done ready for mesh.

- Working on raised floor.

- Working on structure.


Friday (17/6/22)

- Roof done on south side lower side except clear lights.

- Structure almost done with girts and studs outside.



Contractors:

Arthur Brown Construction - www.arthurbrown.co.nz

BTW Company - www.btw.nz

Custom Construction - www.customconstruction.co.nz

Drillco - www.drillco.co.nz

Taranaki Civil Construction - https://www.tccl.co.nz/



Weather Review


























Great buildings come from great people, and all challenges are solved by the execution of a good plan.