Co-Mac Warehouse Build - Week 34
Continued progress as we conclude week 34 of the Co-Mac Warehouse Build. Learn about what happened this week...

Progress Summary
Monday (6/6/22)
- Holiday
Tuesday (7/6/22)
- Intemissent paint seetings put on steelwork
- More girts installed.
- Flashing setting installed.
Wednesday (8/6/22)
- Intemissent paint seetings put on steelwork
- More girts installed.
- Flashing setting installed.
- Working on canopy floor prep.
Thursday (9/6/22)
- Intemissent paint seetings put on steelwork
- More girts installed.
- Flashing setting installed.
- Working on canopy floor prep.
- Raised floor going down.
- Working on canopy floor prep.
Friday (10/6/22)
- Girts installed and bottom plates on walls.
- Raised flooring being done in office.
- Mesh on flooring being done.
Contractors:
Arthur Brown Construction - www.arthurbrown.co.nz
BTW Company - www.btw.nz
Custom Construction - www.customconstruction.co.nz
Drillco - www.drillco.co.nz
Taranaki Civil Construction - https://www.tccl.co.nz/