Co-Mac Warehouse Build - Week 34

Continued progress as we conclude week 34 of the Co-Mac Warehouse Build. Learn about what happened this week...


Progress Summary

Monday (6/6/22)

- Holiday


Tuesday (7/6/22)

- Intemissent paint seetings put on steelwork

- More girts installed.

- Flashing setting installed.


Wednesday (8/6/22)

- Intemissent paint seetings put on steelwork

- More girts installed.

- Flashing setting installed.

- Working on canopy floor prep.


Thursday (9/6/22)

- Intemissent paint seetings put on steelwork

- More girts installed.

- Flashing setting installed.

- Working on canopy floor prep.

- Raised floor going down.

- Working on canopy floor prep.


Friday (10/6/22)

- Girts installed and bottom plates on walls.

- Raised flooring being done in office.

- Mesh on flooring being done.



Contractors:

Arthur Brown Construction - www.arthurbrown.co.nz

BTW Company - www.btw.nz

Custom Construction - www.customconstruction.co.nz

Drillco - www.drillco.co.nz

Taranaki Civil Construction - https://www.tccl.co.nz/