Co-Mac Warehouse Build - Week 33

Continued progress as we conclude week 33 of the Co-Mac Warehouse Build. Learn about what happened this week...


Progress Summary

Monday (30/5/22)

- Lifted roof iron onto roof.

- Put purlins in 1-2.

- Last centre end wall up.

- Strapping on walls of office.



Tuesday (31/5/22)

- Wall strapping in office.

- Fire.

- Purlins in 1-2.

- Working on girts.


Wednesday (1/6/22)

- Fire gib on ceiling.

- Girts and beam in on south wall.

- Started capping on parapet.


Thursday (2/6/22)

- Fire gib installed.

- More girts installed.


Friday (3/6/22)

- Floor started to lay out.

- Wall strapping done.

- Another roof bay done.

- Door lintels in and more girts.

- Working on prep for canopy concrete.



Contractors:

Arthur Brown Construction - www.arthurbrown.co.nz

BTW Company - www.btw.nz

Custom Construction - www.customconstruction.co.nz

Drillco - www.drillco.co.nz

Taranaki Civil Construction - https://www.tccl.co.nz/



Weather Review