Co-Mac Warehouse Build - Week 31
Continued progress as we conclude week 31 of the Co-Mac Warehouse Build. Learn about what happened this week...

Progress Summary
Monday (16/5/22)
- Grid line 4-1 beam lifted on south side.
- Portal 3-2 lifted and purlins installation starting.
- Four joists going in on office and timber batterns.
Tuesday (17/5/22)
- Grid line 4-1 beam lifted up on north side.
- Portal 3-2 lifted and purlin installation started.
- Floor joists done in office.
- Timber batterns going in.
Wednesday (18/5/22)
- Grid line 4-2 purlins getting installed.
- Centre portal grid 4 lifted.
- Floor joists done in office.
- Timber battens installation grid 3-5.
- Roofing put on roof by crane.
Thursday (19/5/22)
- Grid 4-3 centre steel up and some purlins in.
- Battern timber done - nogs to be done.
Friday (20/5/22)
- Office ceiling ready for gib.
Contractors:
Arthur Brown Construction - www.arthurbrown.co.nz
BTW Company - www.btw.nz
Custom Construction - www.customconstruction.co.nz
Drillco - www.drillco.co.nz
Taranaki Civil Construction - https://www.tccl.co.nz/