Co-Mac Warehouse Build - Week 29

Updated: May 9

Continued progress as we conclude week 29 of the Co-Mac Warehouse Build. Learn about what happened this week...


Progress Summary

Monday (2/5/22)

- Boxing removed on office floor.

- W3 mezzanine done for beams.

- Front wall ready to line.

- Door D4 ready to pour.


Tuesday (3/5/22)

- Mezzanine done to W6-1.

- Wall cladding started on front wall.

- Door D4 poured.


Wednesday (4/5/22)

- Front wall cladding.

- Door. D14 poured.

- Working on mezzanine floor


Thursday (5/5/22)

- Front door uprights fitted.

- Girts in on walls.

- Mezzanine floor steel up

- Started on purlins.

- D16 door poured.

- D15 ready to pour.


Friday (6/5/22)

- Mezzanine floor.

- Joists in on first grid line.

- First gird line.

- More cladding up.

- D15 door poured.

- Portal grid 5 lifted in place.



Contractors:

Arthur Brown Construction - www.arthurbrown.co.nz

BTW Company - www.btw.nz

Custom Construction - www.customconstruction.co.nz

Drillco - www.drillco.co.nz

Taranaki Civil Construction - https://www.tccl.co.nz/



Weather Review
























Great buildings come from great people, and all challenges are solved by the execution of a good plan.

5 views0 comments