
Co-Mac Warehouse Build - Week 29
Updated: May 9, 2022
Continued progress as we conclude week 29 of the Co-Mac Warehouse Build. Learn about what happened this week...

Progress Summary
Monday (2/5/22)
- Boxing removed on office floor.
- W3 mezzanine done for beams.
- Front wall ready to line.
- Door D4 ready to pour.
Tuesday (3/5/22)
- Mezzanine done to W6-1.
- Wall cladding started on front wall.
- Door D4 poured.
Wednesday (4/5/22)
- Front wall cladding.
- Door. D14 poured.
- Working on mezzanine floor
Thursday (5/5/22)
- Front door uprights fitted.
- Girts in on walls.
- Mezzanine floor steel up
- Started on purlins.
- D16 door poured.
- D15 ready to pour.
Friday (6/5/22)
- Mezzanine floor.
- Joists in on first grid line.
- First gird line.
- More cladding up.
- D15 door poured.
- Portal grid 5 lifted in place.
Contractors:
Arthur Brown Construction - www.arthurbrown.co.nz
BTW Company - www.btw.nz
Custom Construction - www.customconstruction.co.nz
Drillco - www.drillco.co.nz
Taranaki Civil Construction - https://www.tccl.co.nz/
Weather Review


“Great buildings come from great people, and all challenges are solved by the execution of a good plan.”