Co-Mac Warehouse Build - Week 28
Continued progress as we conclude week 28 of the Co-Mac Warehouse Build. Learn about what happened this week...

Progress Summary
Monday (25/4/22)
- Concrete cut and floor
Tuesday (26/4/22)
- Acron sprayed on floor.
- 1/2 boxing removed on office floor.
- Steel up on west wall.
Wednesday (27/4/22)
- Working on steel on the west wall.
- Roofers on site.
Thursday (28/4/22)
- Got flashings done up on roof.
- Started mezzanine floor W1.
- Done door truck supports on D18
Friday (29/4/22)
- Acron down.
- Roof 12-9 Done
- Mezzanine floor done W1-W3.
- Door boxed to pour D17/16.
- Started on D15 & D4
Contractors:
Arthur Brown Construction - www.arthurbrown.co.nz
BTW Company - www.btw.nz
Custom Construction - www.customconstruction.co.nz
Drillco - www.drillco.co.nz
Taranaki Civil Construction - https://www.tccl.co.nz/
Weather Review


“Great buildings come from great people, and all challenges are solved by the execution of a good plan.”