Co-Mac Warehouse Build - Week 27
Continued progress as we conclude week 27 of the Co-Mac Warehouse Build. Learn about what happened this week...

Progress Summary
Monday (18/4/22)
- Holiday. (Easter Monday)
Tuesday (19/4/22)
- Roofer turned up and put plastic under clear roofing.
Wednesday (20/4/22)
- Floor ready to poor.
- Steal girts up in front walls.
Thursday (21/4/22)
- Floor poured.
Friday (22/4/22)
- Acron down.
- Working on end walls, girls and side wall ready for lift. 5/4 centre lift.
Saturday (23/4/22)
- Roofing going on.
- 12 - 9 South side finished.