Co-Mac Warehouse Build - Week 27

Continued progress as we conclude week 27 of the Co-Mac Warehouse Build. Learn about what happened this week...


Progress Summary

Monday (18/4/22)

- Holiday. (Easter Monday)


Tuesday (19/4/22)

- Roofer turned up and put plastic under clear roofing.


Wednesday (20/4/22)

- Floor ready to poor.

- Steal girts up in front walls.


Thursday (21/4/22)

- Floor poured.


Friday (22/4/22)

- Acron down.

- Working on end walls, girls and side wall ready for lift. 5/4 centre lift.


Saturday (23/4/22)

- Roofing going on.

- 12 - 9 South side finished.



Contractors:

Arthur Brown Construction - www.arthurbrown.co.nz

BTW Company - www.btw.nz

Custom Construction - www.customconstruction.co.nz

Drillco - www.drillco.co.nz

Taranaki Civil Construction - https://www.tccl.co.nz/



Weather Review





















Great buildings come from great people, and all challenges are solved by the execution of a good plan.

15 views0 comments

Recent Posts

See All
bottom of page