Co-Mac Warehouse Build - Week 26
Continued progress as we conclude week 26 of the Co-Mac Warehouse Build. Learn about what happened this week...

Progress Summary
Monday (11/4/22)
- Plumbing/drainage done ready for floor pour.
- 3/4 Floor prep done ready to pour.
Tuesday (12/4/22)
- Almost ready to pour office floor.
Wednesday (13/4/22)
- Floor read to poor
Thursday (14/4/22)
- ABC boxed up for footings on front door and side sliding door. South side.
Friday (15/4/22)
- Holiday (Good Friday)
Contractors:
Arthur Brown Construction - www.arthurbrown.co.nz
BTW Company - www.btw.nz
Custom Construction - www.customconstruction.co.nz
Drillco - www.drillco.co.nz
Taranaki Civil Construction - https://www.tccl.co.nz/
Weather Review