Co-Mac Warehouse Build - Week 25
Continued progress as we conclude week 25 of the Co-Mac Warehouse Build. Learn about what happened this week...

Progress Summary
Monday (4/4/22)
- 6 - 12 done.
- 5 - 4 ready to lift on south side.
- Beam lifted on south side 7 -4.
- Office floor prep doing.
- Boxing going in on floor.
- Roofer done mesh on 12- 9.
Tuesday (5/4/22)
- Lift 5 - 4 south side and put in purlins.
- Leveled office floor.
- Boxing done on office floor.
Wednesday (6/4/22)
- North centre beam
- Up on 5 - 3.
- 5 - 4 ready to lift on Northside.
- Sparky finished putting in pipework under office floor.
Thursday (7/4/22)
- Electrical done.
- Plumbing done for back toilet under floor.
- 5 - 3 ready to lift south side.
- 5 - 3 centre ready to lift.
Friday (8/4/22)
- Roofers did North 12 - 9 bottom half.
- Plumbers did boardroom and toilet block piping.
- 5 - 3 Lifted Southside bottom side.
- Ready for 5/4 centre lift.
Saturday (9/4/22)
- Roofers did south 12 - 9 bottom.
Contractors:
Arthur Brown Construction - www.arthurbrown.co.nz
BTW Company - www.btw.nz
Custom Construction - www.customconstruction.co.nz
Drillco - www.drillco.co.nz
Taranaki Civil Construction - https://www.tccl.co.nz/
Weather Review


“Great buildings come from great people, and all challenges are solved by the execution of a good plan.”