Co-Mac Warehouse Build - Week 25

Continued progress as we conclude week 25 of the Co-Mac Warehouse Build. Learn about what happened this week...


Progress Summary

Monday (4/4/22)

- 6 - 12 done.

- 5 - 4 ready to lift on south side.

- Beam lifted on south side 7 -4.

- Office floor prep doing.

- Boxing going in on floor.

- Roofer done mesh on 12- 9.


Tuesday (5/4/22)

- Lift 5 - 4 south side and put in purlins.

- Leveled office floor.

- Boxing done on office floor.


Wednesday (6/4/22)

- North centre beam

- Up on 5 - 3.

- 5 - 4 ready to lift on Northside.

- Sparky finished putting in pipework under office floor.


Thursday (7/4/22)

- Electrical done.

- Plumbing done for back toilet under floor.

- 5 - 3 ready to lift south side.

- 5 - 3 centre ready to lift.


Friday (8/4/22)

- Roofers did North 12 - 9 bottom half.

- Plumbers did boardroom and toilet block piping.

- 5 - 3 Lifted Southside bottom side.

- Ready for 5/4 centre lift.


Saturday (9/4/22)

- Roofers did south 12 - 9 bottom.




Contractors:

Arthur Brown Construction - www.arthurbrown.co.nz

BTW Company - www.btw.nz

Custom Construction - www.customconstruction.co.nz

Drillco - www.drillco.co.nz

Taranaki Civil Construction - https://www.tccl.co.nz/



Weather Review