Co-Mac Warehouse Build - Week 24

Continued progress as we conclude week 24 of the Co-Mac Warehouse Build. Learn about what happened this week...


Progress Summary

Monday (28/3/22)

- Setting up 6 and 7 centre purlins and 5 legs.

- ABC working on office floor foundations.

- Waiting for top end piece.


Tuesday (29/3/22)

- Working on 5 - 6 1/3 End.

- Working on boxing for floor.


Wednesday (30/3/22)

- Putting up centre on 9 - 8 - 7 centre piece.

- Finishing floor inside footings and pads.


Thursday (31/3/22)

- Concrete foundation and pads done inside office.


Friday (1/4/22)

- Pad boxing stripped and started on boxing the floor.

- 7-10 almost completed. Small pieces to be done.


Contractors:

Arthur Brown Construction - www.arthurbrown.co.nz

BTW Company - www.btw.nz

Custom Construction - www.customconstruction.co.nz

Drillco - www.drillco.co.nz

Taranaki Civil Construction - https://www.tccl.co.nz/



Weather Review























Great buildings come from great people, and all challenges are solved by the execution of a good plan.

2 views0 comments