Co-Mac Warehouse Build - Week 24
Continued progress as we conclude week 24 of the Co-Mac Warehouse Build. Learn about what happened this week...

Progress Summary
Monday (28/3/22)
- Setting up 6 and 7 centre purlins and 5 legs.
- ABC working on office floor foundations.
- Waiting for top end piece.
Tuesday (29/3/22)
- Working on 5 - 6 1/3 End.
- Working on boxing for floor.
Wednesday (30/3/22)
- Putting up centre on 9 - 8 - 7 centre piece.
- Finishing floor inside footings and pads.
Thursday (31/3/22)
- Concrete foundation and pads done inside office.
Friday (1/4/22)
- Pad boxing stripped and started on boxing the floor.
- 7-10 almost completed. Small pieces to be done.
Contractors:
Arthur Brown Construction - www.arthurbrown.co.nz
BTW Company - www.btw.nz
Custom Construction - www.customconstruction.co.nz
Drillco - www.drillco.co.nz
Taranaki Civil Construction - https://www.tccl.co.nz/
Weather Review


“Great buildings come from great people, and all challenges are solved by the execution of a good plan.”