Co-Mac Warehouse Build - Week 22

Continued progress as we conclude week 22 of the Co-Mac Warehouse Build. Learn about what happened this week...


Progress Summary

Monday (14/3/22)

- Public Holiday.


Tuesday (15/3/22)

- Purlins arrived.

- ABC working on the floor.

- Working on purlins and portals.


Wednesday (16/3/22)

- Pads ready to pour in office.

- Working on 8 - 9 grid centre and 7 & 6.


Thursday (17/3/22)

- Pads ready for inspection for mezzanine floor.

- Footing started on office wall.

- Grid 8 & 9 up, and purlins in. Waiting on end grids to hold mesh.


Friday (18/1/22)

- Eight grid lines braced and done.

- Six pads ready to pour on office floor.


Contractors:

Arthur Brown Construction - www.arthurbrown.co.nz

BTW Company - www.btw.nz

Custom Construction - www.customconstruction.co.nz

Drillco - www.drillco.co.nz

Taranaki Civil Construction - https://www.tccl.co.nz/



Weather Review

















Great buildings come from great people, and all challenges are solved by the execution of a good plan.