Co-Mac Warehouse Build - Week 20

Continued progress as we conclude week 20 of the Co-Mac Warehouse Build. Learn about what happened this week...


Progress Summary

Monday (28/2/22)

- Other purlins are going to be cut down to suit.

- Started cutting burn purlins.

- Braces getting installed.

- Purlins getting installed.


Tuesday (1/3/22)

- Put centre section on our grid line.

- Put purlins in on grid line 12.


Wednesday (2/3/22)

- Setting up for installing main beam and grid line lift.

- Installing braces.


Thursday (3/3/22)

- Centre beam installed.

- Grid line 9 installed & gridline 10 put purlins in.

- Scaffolding crew doing walls and roof.


Friday (4/3/22)

- Getting ready for grid 9 next lift.


Contractors:

Arthur Brown Construction - www.arthurbrown.co.nz

BTW Company - www.btw.nz

Custom Construction - www.customconstruction.co.nz

Drillco - www.drillco.co.nz

Taranaki Civil Construction - https://www.tccl.co.nz/



Weather Review















Great buildings come from great people, and all challenges are solved by the execution of a good plan.