Co-Mac Warehouse Build - Week 2

It has been another successful week on Kerry Lane! The contractors have been busy making progress and we're on track for the first stage of foundation next week.


Progress Summary

This week the holes for the portal foundations were dug and the site was finished being marked out. There was also more progress with the drilling for the HVAC pipes.




Contractors:

Arthur Brown Construction - www.arthurbrown.co.nz

BTW Company - www.btw.nz

Custom Construction - www.customconstruction.co.nz

Taranaki Civil Construction - https://www.tccl.co.nz/



Weather Review


We had a decent week of weather, no rain for the majority of the week with just a few showers on Thursday. and most importantly the security fence survived another week of the Taranaki wind.




Weekly Project Rating


Weekly Grade: 8/10

It was nice to see another week of progress, we're looking forward to the first stage of the foundation starting next week.






Great buildings come from great people, and all challenges are solved by the execution of a good plan.