Continued progress as we conclude week 19 of the Co-Mac Warehouse Build. Learn about what happened this week...


Progress Summary

Monday (21/2/22)

- Another Truck arrived with purlins and portals.

- Installed wall members.


Tuesday (22/2/22)

- Another truck arrived.

- Installed wall members.


Wednesday (23/2/22)

- No one on site.


Thursday (24/2/22)

- Scaffolding done.

- Grid 12 - 10.

- No one working on building structure.


Friday (25/2/22)

- No one on site


Contractors:

Arthur Brown Construction - www.arthurbrown.co.nz

BTW Company - www.btw.nz

Custom Construction - www.customconstruction.co.nz

Drillco - www.drillco.co.nz

Taranaki Civil Construction - https://www.tccl.co.nz/



Weather Review
















Great buildings come from great people, and all challenges are solved by the execution of a good plan.