Progress Summary
Monday (21/2/22)
- Another Truck arrived with purlins and portals.
- Installed wall members.
Tuesday (22/2/22)
- Another truck arrived.
- Installed wall members.
Wednesday (23/2/22)
- No one on site.
Thursday (24/2/22)
- Scaffolding done.
- Grid 12 - 10.
- No one working on building structure.
Friday (25/2/22)
- No one on site