Co-Mac Warehouse Build - Week 18
Continued progress as we conclude week 18 of the Co-Mac Warehouse Build. Learn about what happened this week...

Progress Summary
Monday (14/2/22)
- Repaired security fence that storm blew down.
- Truck with purlins arrived.
- Started putting purlins onto portals.
Tuesday (15/2/22)
- Put posts up on grid 11 & 10 outside.
Wednesday (16/2/22)
- Lifted grid.
- 10 - 11 1/3 roof up.
- On D to C.1
Thursday (17/2/22)
- Lifted 1/3 roof up on B - B.2 Grid 10 - 11.
- Started assembly on ground of mid roof section on B.2 - C.1 Grid 10-11.
Friday (18/2/22)
- Finished mid roof section.
- Worked on end wall dwangs.