Progress Summary

Monday (14/2/22)

- Repaired security fence that storm blew down.

- Truck with purlins arrived.

- Started putting purlins onto portals.


Tuesday (15/2/22)

- Put posts up on grid 11 & 10 outside.


Wednesday (16/2/22)

- Lifted grid.

- 10 - 11 1/3 roof up.

- On D to C.1


Thursday (17/2/22)

- Lifted 1/3 roof up on B - B.2 Grid 10 - 11.

- Started assembly on ground of mid roof section on B.2 - C.1 Grid 10-11.


Friday (18/2/22)

- Finished mid roof section.

- Worked on end wall dwangs.


Contractors:

Arthur Brown Construction - www.arthurbrown.co.nz

BTW Company - www.btw.nz

Custom Construction - www.customconstruction.co.nz

Drillco - www.drillco.co.nz

Taranaki Civil Construction - https://www.tccl.co.nz/



Weather Review
























Great buildings come from great people, and all challenges are solved by the execution of a good plan.

0 views0 comments

Recent Posts

See All
bottom of page