Co-Mac Warehouse Build - Week 16

Continued progress as we conclude week 16 of the Co-Mac Warehouse Build. Learn about what happened this week...


Progress Summary

Monday (31/1/22)

- Working on down pipes

- Finished Sumps


Tuesday (1/2/22)

- Coresteel truck came.

- Working on down pipes.

- Laying out Coresteel parts.


Wednesday (2/2/22)

- Down pipes finished.

- Assembling grid line portal.

- 11 & 12 is on ground ready for purlins.


Thursday (3/2/22)

- General tidy up.

- JE putting brackets on the legs & portals ready for purlins.


Friday (4/2/22)

- No one on site.


Contractors:

Arthur Brown Construction - www.arthurbrown.co.nz

BTW Company - www.btw.nz

Custom Construction - www.customconstruction.co.nz

Drillco - www.drillco.co.nz

Taranaki Civil Construction - https://www.tccl.co.nz/



Weather Review


















Great buildings come from great people, and all challenges are solved by the execution of a good plan.

1 view0 comments

Recent Posts

See All
bottom of page