Co-Mac Warehouse Build - Week 16
Continued progress as we conclude week 16 of the Co-Mac Warehouse Build. Learn about what happened this week...

Progress Summary
Monday (31/1/22)
- Working on down pipes
- Finished Sumps
Tuesday (1/2/22)
- Coresteel truck came.
- Working on down pipes.
- Laying out Coresteel parts.
Wednesday (2/2/22)
- Down pipes finished.
- Assembling grid line portal.
- 11 & 12 is on ground ready for purlins.
Thursday (3/2/22)
- General tidy up.
- JE putting brackets on the legs & portals ready for purlins.
Friday (4/2/22)
- No one on site.