Co-Mac Warehouse Build - Week 11
Updated: Jan 10, 2022
Continued progress as we conclude week 11 of the Co-Mac Warehouse Build. Learn about what happened this week...

Progress Summary
Monday (20/12/21)
- North side almost ready to pour foundation.
Tuesday (21/12/21)
- North side ready to pour concrete.
Wednesday (22/12/21)
- North side foundation poured and all internals pads poured aswell.
Contractors:
Arthur Brown Construction - www.arthurbrown.co.nz
BTW Company - www.btw.nz
Custom Construction - www.customconstruction.co.nz
Drillco - www.drillco.co.nz
Taranaki Civil Construction - https://www.tccl.co.nz/