Co-Mac Warehouse Build - Week 10

Continued progress as we conclude week 10 of the Co-Mac Warehouse Build. Learn about what happened this week...


Progress Summary

Monday (13/12/21)

- North side boxed externally and braced.

- Reinforcing done on North side.


Tuesday (14/12/21)

- East side boxed and braced on exterior.

- Reinforcing half done on East side.

- Internal pads boxed.

- Office area ready to pour.

- Outside boxing in canopy legs.


Wednesday (15/12/21)

- All inside pads ready to pour.

- Outside pads for canopy has reinforcing in place.

- All foundation reinforcing and boxes for the PT floor in place.


Thursday (16/12/21)

- External canopy bases poured.


Friday (17/12/21)

- Inside boxing 80% completed on North side.


Contractors:

Arthur Brown Construction - www.arthurbrown.co.nz

BTW Company - www.btw.nz

Custom Construction - www.customconstruction.co.nz

Drillco - www.drillco.co.nz

Taranaki Civil Construction - https://www.tccl.co.nz/



Weather Review
















Great buildings come from great people, and all challenges are solved by the execution of a good plan.