Co-Mac Warehouse Build - Week 10
Continued progress as we conclude week 10 of the Co-Mac Warehouse Build. Learn about what happened this week...

Progress Summary
Monday (13/12/21)
- North side boxed externally and braced.
- Reinforcing done on North side.
Tuesday (14/12/21)
- East side boxed and braced on exterior.
- Reinforcing half done on East side.
- Internal pads boxed.
- Office area ready to pour.
- Outside boxing in canopy legs.
Wednesday (15/12/21)
- All inside pads ready to pour.
- Outside pads for canopy has reinforcing in place.
- All foundation reinforcing and boxes for the PT floor in place.
Thursday (16/12/21)
- External canopy bases poured.
Friday (17/12/21)
- Inside boxing 80% completed on North side.
Contractors:
Arthur Brown Construction - www.arthurbrown.co.nz
BTW Company - www.btw.nz
Custom Construction - www.customconstruction.co.nz
Drillco - www.drillco.co.nz
Taranaki Civil Construction - https://www.tccl.co.nz/
Weather Review


“Great buildings come from great people, and all challenges are solved by the execution of a good plan.”